Which of the following is not an advantage of unit price contracts?
A、The Contractor is paid for the amount of actual work he does.;
B、While remaining a fair basis for payment there is freedom for the alteration of work.;
C、Little supervision on the execution of the work is required from the Employer and the Engineer.;
D、The tenderer is given a clear conception of the work involved by the way of bills.