请在 下方输入 要搜索的题目:

一名工程师在没有提交变更请求的情况下,完成一名项目相关方的可 交付成果变更要求。项目经理应该怎么做?  An engineer completes a stakeholder request for a change in a deliverable without submitting a change request. What should the project manager do?  A :获得为何进行变更的相关信息 Obtain information about why the change was made  B : 审查变更的影响,并提交变更请求 Review the impact of the change, and submit a change request  C :更新问题日志 Update the issue log  D :指示该工程师撤销变更 Instru ct the engineer to undo the change

一名工程师在没有提交变更请求的情况下,完成一名项目相关方的可 交付成果变更要求。项目经理应该怎么做?  An engineer completes a stakeholder request for a change in a deliverable without submitting a change request. What should the project manager do?  A :获得为何进行变更的相关信息 Obtain information about why the change was made  B : 审查变更的影响,并提交变更请求 Review the impact of the change, and submit a change request  C :更新问题日志 Update the issue log  D :指示该工程师撤销变更 Instru ct the engineer to undo the change

发布时间:2024-07-01 10:23:12
推荐参考答案 ( 由 搜搜题库网 官方老师解答 )
联系客服
答案:
搜搜题找答案
用户信息
没有账号?点我注册
登录 - 搜搜题库网
立即注册
注册 - 搜搜题库网
验证码
立即登录