Lesley Torres is a project manager for the campaign "Action against Deforestation in Indonesia." She recently faced a glitch when the campaign could not be launched publicly according to schedule. Torres monitored the schedule to find the cause of the delay before speeding up the implementation process by allocating more members for the implementation phase. By doing this, which of the following functions is she performing?
A、controlling
B、planning
C、formulating
D、leading
E、organizing
发布时间:2024-09-13 14:37:46