【单选题 4 选 1】The program manager is concerned the program scope cannot be met with the available internal and external resource. How should the program manager evaluate these concerns?
A、Meetwithprogrammanagementofficetoreviewthecriticalprogramsuccessfactor.
B、Meetwithcomponentprojectmanagertoassesstheimpactonprogramperformanceoutcome.
C、Meetwithstakeholdertodetermineifareductioninprogramscopetsacceptable.
D、Meetwiththecomponentprojectmanagertooptimizeresourceallocation?*withintheprogram.